DONES

Pre-Commercial Public Procurement for the development of validators systems and materials for fusion energy

validadores de sistemas y materiales en energía

 

Tender CPP 01-2024

 

Identified need

IFMIF-DONES (International Fusion Materials Irradiation Facility, DEMO Oriented Neutron Source) is the scientific infrastructure that the consortium IFMIF-DONES Spain will help to build and operate in Escúzar (Granada). This future major Scientific was unique to the international level and has been included in the road map for the achievement of fusion energy and the list of the european strategic infrastructures (ESFRI).

IFMIF-DONES is a source of neutrons, essential to test the most critical material installations, which makes it unique in the world, but also makes it an important technological baseline for many other scientific or industrial facilities that are under construction or are in the project.

The objective of this contract is the development of Technological Validators integrated systems of the Accelerator (VATIAC) and systems in the area of Test (VATIST), which will enable the Consortium of performing long-term critical systems and components for the future major international scientific IFMIF-DONES.

 

Public Entity issuing the challenge

Consortium IFMIF-DONES Spain

Logo JPG

 

Technological challenge awarded

  • Tender budget: 48.400.000 Eur (vat)
  • Period: 40 months
  • 2 TENDER LOTS:

- LOT 1 (VATIAC): 32.670.000 (vat)

- LOT 2 (VATIST): 15.730.000 (vat)

  • Contract awardees:
    • Phase 1 (Design of the solution)
      • LOT 1 (VATIAC)
        • UTE EMPRESARIOS AGRUPADOS INTERNACIONAL S.A., SUPRASYS S.L., EDAIR TECHNOLOGIES S.L., HI-IBERIA INGENIERIA Y PROYECTOS S.L., COMMTIA SYSTEMS S.A., ANTEC MAGNETS S.L.U.
        • UTE AVS ADDED VALUE INDUSTRIAL ENGINEERING SOLUTIONS S.L., BROAD TELECOM S.A. (BTESA)
      • LOT 2 (VATIST)
        • UTE ASTURFEITO S.A., EMPLOYERS GROUPED INTERNATIONAL S.A., INGECID S.L.
    • Phase 2 (Development of prototypes)
      • LOT 1 (VATIAC)
        • UTE AVS ADDED VALUE INDUSTRIAL ENGINEERING SOLUTIONS S.L., BROAD TELECOM S.A. (BTESA)
      • LOT 2 (VATIST)
        • UTE ASTURFEITO S.A., EMPLOYERS GROUPED INTERNATIONAL S.A., INGECID S.L.
    • Phase 3 (Preoperational validation)

 

Milestones

  • [2026/03/13]: Launghing of phase 2 (lot 2, VATIST)
  • [2025/11/05]: Launghing of phase 2 (lot 1, VATIAC)
  • [2025/01/13]: Launching of phase 1
  • [2025/01/10]: Conclusion of contracts.
  • [2024/12/30]: Award the contracts.
  • [2024/06/24]: Day for the submission of the Solicitation Documents (presentations and video available).
  • [2024/06/04]: Publication of tender and solicitation documents in thePLACSP. Submission of tenders until 3 september 2024.
  • [2023/08/21 and 2024/01/26]: signing of adendas to the convention for enlargement of THE AMOUNT (1St addition)time frame, and origin of funds (2Nd codicil).
  • [2023/06/02): Published the final report of findings of the jpc in PLACSP.
  • [2023/04/12]: Signing of the convention between CDTI and the Consortium IFMIF-DONES Spain.
  • [2023/01/18]: Submission of the preparatory consultation of the market (Day).
  • [2022/12/23]: Convening of the preparatory consultation of the market (CPM).

 

Initiative cofinanced by the european Regional development fund (ERDF) in operational program 2021-2027 Plurirregional of Spain